Kentish Town Station – Platform, Passageway and Ticket Hall Works

7 Star Construction delivered a comprehensive package of premises, finishing and structural works as part of the major refurbishment of Kentish Town Underground Station.

The initial package covered extensive plastering and finishing works across the station platforms and connecting passageways. Approximately 1,100m² of wall surfaces were repaired, rendered and finished, including around 380m² at platform level and a further 720m² through the passageways.

These activities were completed during restricted engineering-hours shifts, requiring careful daily planning, controlled material movement, and efficient use of each available working window. Rapid-setting repair and rendering materials were used where required to achieve the specified finish within the limited shift periods and allow subsequent trades to progress.

The team also completed approximately 470m² of high-level painting. This included preparing and repairing existing surfaces followed by applying the specified paint system, helping create the clean, bright environment visible throughout the refurbished station.

Secure POM Room Construction
A later package involved constructing a new secure Passenger Operated Machine (POM) room within the ticket hall. The room was formed using reinforced blockwork incorporating stainless-steel bed-joint reinforcement, wall starters, wall ties, head restraints and concrete lintels.

Security mesh was incorporated into the enclosure, with rendered, skimmed and painted finishes applied to the designated wall surfaces. Fermacell lining was also installed where required. Unlike the platform works, the POM-room construction was undertaken during daytime shifts and carefully coordinated with the other contractors operating throughout the ticket hall.

Deliveries and material movements required detailed planning because blocks, reinforcement, render, concrete components and finishing materials had to be transported from outside the station to their final installation positions. The room was completed within a tightly controlled six-week programme while the wider project team worked towards reopening the station before Christmas.